Traffic Signal, Pedestrian & Bicycle Improvements

  • Project value$989,898.00
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 15, 2024
Prairie Ave at 10th & 11th location map

Project Update 9/30/2024

  • Removals, Concrete work, and Underground Signal work has been completed for Phase 1. Concrete has been poured for the ramps, sidewalk, fillets, and the traffic signal bases and controller cabinet foundation.
  • Concrete work for Phase 2 will finish early October. Restoration will begin after that. Expect intermittent lane closures while landscaping.
  • Signal Equipment is expected to arrive in mid October. Intermittent lane closures are to be expected while installing overhead signal equipment.

Commuter Route Information

  • 10th Street and 11th Street are both reduced to two lanes.

Project Milestones

Prairie Avenue & 10th Street

  1. Concrete removals
  2. Concrete curb ramp, sidewalk and fillets construction
  3. Pavement marking installation
  4. Traffic Signal Installation
  5. Restoration

Prairie Avenue & 11th Street

  1. Concrete removals
  2. Concrete curb ramp, sidewalk and fillets construction
  3. Pavement marking installation
  4. Traffic Signal Installation
  5. Restoration