26th Street Overlay- Cleveland Avenue to Alpine Avenue

  • Project value$2,398,392
  • Contractor nameBlack-Top Paving
26th-Street-project-location

Project Update 10/31/2023

  • This will be the final project update.
  • All paving has been completed.
  • Manhole & valve box adjustments need to be completed before opening the north side to traffic.
  • The road will be fully open to traffic by mid-November.

Commuter Route Information:  

  • 26th Street is reduced to one lane of traffic in each direction between Cleveland Avenue and Alpine Avenue
  • Pedestrians should utilize the sidewalk on the south side of 26th Street.

Project Milestones

Phase 1A
Traffic will be reduced to the southern two lanes between Cleveland Avenue and Bahnson Avenue, with one lane in each direction.

  1. Complete storm sewer repairs.
  2. Complete ADA ramp improvements.
  3. Cold mill concrete pavement.
  4. Asphalt patching.
  5. Asphalt overlay.

Phase 1B
Traffic will be reduced to the southern two lanes between Bahnson Avenue & Alpine Avenue, with one lane in each direction.

  1. Complete ADA ramp improvements.
  2. Cold mill concrete pavement.
  3. Asphalt patching.
  4. Asphalt overlay.

Phase 2A
Traffic will be reduced to the northern two lanes between Cleveland Avenue & Bahnson Avenue, with one lane in each direction.

  1. Complete ADA ramp improvements.
  2. Cold mill concrete pavement.
  3. Asphalt patching.
  4. Asphalt overlay.

Phase 2B
Traffic will be reduced to the northern two lanes between Bahnson Avenue & Alpine Avenue, with one lane in each direction.

  1. Complete ADA ramp improvements.
  2. Cold mill concrete pavement.
  3. Asphalt patching.
  4. Asphalt overlay.