10th Street Improvements from I-229 to Sycamore Avenue

  • Project value$2,292,296.52
  • Contractor nameAsphalt Surfacing Company
  • Completion DateSeptember 15, 2024

Project Update 6/28/2024 

  • Grading on Blaine Avenue is complete, and paving work will begin soon.  Along 10th Street, storm drainage work and the pavement repairs are complete.  Asphalt paving for south side lane widening as well as accessible curb ramp repairs will begin soon.

Commuter Route Information

  • Eastbound traffic is reduced to one lane. Westbound traffic is not impacted at this time.

Project Milestones

Phase 1:

  1. Lane closures of outside lanes along 10th Street
  2. Lane widening
  3. Blaine Avenue cul-de-sac
  4. Storm sewer installation and repairs
  5. Curb & gutter repairs
  6. Traffic signal and lighting improvements
  7. Fillet, accessible curb ramp and sidewalk improvements
  8. Concrete milling
  9. Asphalt overlay
  10. Manhole and water valve adjustments

Phase 2:

  1. Lane closures of inside lanes along 10th Street
  2. Median repairs
  3. Asphalt overlay
  4. Manhole and water valve adjustments
  5. Pavement markings
  6. Seeding and landscaping