Klein Ave Neighborhood Reconstruction–Street and Utility Improvements

  • Project value$720,000
  • Contractor nameSoukup Construction
  • Completion DateSeptember 27, 2024

Project Update 6/28/2024

  • All sanitary sewer work is complete.  Watermain work is in progress in Phase 2.  Storm drainage work and roadway grading will begin in July after the watermain work has been completed.

Commuter Route Information

  • Klein Avenue is closed to traffic. Local access for the area is from the south via the intersection of 46th & Klein.  

Project Milestones

Phase 1: The intersection of 41st Street and Klein Avenue south leg

  1. Utility tie in connections
  2. Pavement replacement

Phase 2: Klein Avenue 41st Street to 42nd Street

  1. Removals
  2. Sanitary sewer
  3. Watermain
  4. Storm sewer
  5. Grading and shaping
  6. Concrete curb and gutter/sidewalk
  7. Asphalt surfacing
  8. Signage and street lights
  9. Restoration