Traffic Signal, Pedestrian & Bicycle Improvements

  • Project value$989,898.00
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 15, 2024
Prairie Ave at 10th & 11th location map

Project Update 9/3/2024

  • Removals, concrete work, and underground signal work has been completed for Phase 1. Concrete has been poured for the ramps, sidewalk, fillets, traffic signal bases, and controller cabinet foundation.
  • Removals and Concrete work for Phase 2 is scheduled to begin the first week of September. Traffic will be switched at that time.
  • Phase 2 will close the south half of each intersection, at both 10th/Prairie and 11th/Prairie. There will be two lanes of traffic maintained on 10th Street and 11th Street.
  • Signal Equipment has been ordered and is expected to arrive in early October.

Commuter Route Information

  • 10th Street and 11th Street are both reduced to two lanes.

Project Milestones

Prairie Avenue & 10th Street

  1. Concrete removals
  2. Concrete curb ramp, sidewalk and fillets construction
  3. Pavement marking installation
  4. Traffic Signal Installation
  5. Restoration

Prairie Avenue & 11th Street

  1. Concrete removals
  2. Concrete curb ramp, sidewalk and fillets construction
  3. Pavement marking installation
  4. Traffic Signal Installation
  5. Restoration