Bridge Preservation – Russell Street Bridges

  • Project valueEngineer’s cost estimate = $596,055
  • Contractor nameTBD
  • Completion DateOctober 15, 2024
Russell Street Bridge Map

Project Update 4/2/2024

This project is scheduled to bid on Thursday, April 4, 2024.

Commuter Route Information

  • Lane closures will be in place.
  • At a minimum, one lane of traffic will remain open in both directions at all times.

Project Milestones

Westbound Bridge

  1. Concrete bridge deck repair
  2. Polymer chip seal
  3. Special surface finish
  4. Berm repair

Eastbound Bridge

  1. Concrete bridge deck repair
  2. Polymer chip seal
  3. Special surface finish
  4. Berm repair