Sycamore Ave Concrete Rehab from Arrowhead Parkway to Madison St.

  • Project value$2,664,126
  • Contractor nameDakota Contracting Corporation
  • Completion DateNovember 08, 2024
Sycamore Project Map

Project Update 4/2/2024

This project is anticipated to begin in May 2024.

Commuter Route Information

  • Lane closures will be in place.
  • At a minimum, one lane of traffic will remain open in both directions at all times.
  • Every effort will be made to minimize traffic disruption by Washington High School when school is in session.

Project Milestones

  1. Curb & gutter and fillet repairs
  2. Concrete panel and joint repairs
  3. Partial depth pavement repairs
  4. Accessible sidewalk replacement/li>
  5. Seeding & topsoil placement
  6. Diamond grinding of concrete pavement surface
  7. Reseal concrete pavement joints
  8. Pavement Markings