Veterans Concrete Restoration & Joint Reseal from Arrowhead to 26th

  • Project valueTBD
  • Contractor nameTBD
  • Completion DateNovember 15, 2024
Veteran's Arrowhead to 26th St. Project Map

Project Update 4/2/2024

This project is in the design stage.

Commuter Route Information

  • This project is anticipated to begin in June 2024. 
  • Lane closures will be in place. 
  • At a minimum, one lane of traffic will remain open in both directions at all times.

Project Milestones

  1. Curb & gutter and fillet repairs
  2. Concrete panel and joint repairs
  3. Seeding & topsoil placement
  4. Application of soy based penetrating sealer
  5. Reseal concrete pavement joints