Tallgrass Avenue from 74th Street to 89th Street

  • Contractor nameT&R Contracting, Inc.
  • Completion DateDecember 13, 2024
Tallgrass-74th-St-to-85th-St

Project Update 6/3/2024

  • Contractor is installing Underdrains along Tallgrass Avenue from 74th street to 85th street.
  • Contractor is currently working on installing fabric and gravel along Tallgrass Avenue from 77th street to 85th street.
  • The intersection of 85th and Tallgrass Avenue will be open to traffic by end of June.

Commuter Route Information:  

  • Tallgrass Avenue from 74th street to 89th street will be closed to traffic.
  • Access will be maintained to local residents only.

Phase 1 Project Milestones

  1. Road Closed
  2. Removals
  3. Sanitary sewer
  4. Watermain
  5. Storm Sewer
  6. Grading
  7. Subgrade Stabilization
  8. Graveling
  9. Curb and Gutter
  10. Concrete Surfacing
  11. Restoration
  12. Open to Traffic

Phase 2 Project Milestones

  1. Road Closed
  2. Removals
  3. Grading
  4. Subgrade Stabilization
  5. Graveling
  6. Curb & Gutter
  7. Concrete Surfacing
  8. Lighting
  9. Restoration
  10. Open to Traffic