  • Project was bid April 18, 2024 and ASCO from Sioux Falls was read low at $2,544,126.50. Anticipated project start date of May 28th.
  • A Public Open House is planned for May 20th from 5:00pm to 7:00pm at Axtell Park Middle School, 201 N. West Avenue, to discuss any concerns regarding the project. A letter will also be sent out to the property owners prior to the Open House.  

Commuter Route Information:

*A Press Release will be issued prior to the closure of Phase 1 along 10th Street from West Avenue to Menlo Avenue

  • Phase 1 – 10th Street will be closed from West Avenue to Euclid Avenue. Detour will be 9th Street or 12th Street.  Pedestrian access will always be available on one side of the street.
  • Phase 2 – 10th Street will be closed from Euclid Avenue to Menlo Avenue.  Detour will be 9th Street or 12th Street.  Pedestrian access will always be available on one side of the street.
  • Phase 3 – Covell Avenue will be closed from 11th Street to 10th Street.  Detour will be either Lake Avenue or Euclid Avenue.  Pedestrian access will always be available on one side of the street.
  • Phase 4 – Menlo Avenue wil be closed from 10th Street to 9th Street.  Detour will be either Walts Avenue or Grange Avenue. Pedestrian access will always be available on one side of the street.

Project Milestones

Phase 1: 10th Street – West Ave to Euclid Ave

  1. Removals
  2. Sanitary sewer
  3. Water main
  4. Concrete work
  5. Lighting
  6. Street paving
  7. Traffic Striping
  8. Restoration

Phase 2: 10th Street – Euclid Ave to Menlo Ave

  1. Removals
  2. Sanitary sewer
  3. Water main
  4. Concrete work
  5. Lighting
  6. Street paving
  7. Traffic Striping
  8. Restoration

Phase 3: Covell Ave – 11th to 10th Street

  1. Removals
  2. Sanitary sewer
  3. Water main
  4. Concrete work
  5. Lighting
  6. Street paving
  7. Restoration

Phase 4: Menlo Ave – 10th to 9th Street

  1. Removals
  2. Water main
  3. Concrete work
  4. Lighting
  5. Street paving
  6. Restoration