85th Street Improvements – Sundowner Avenue to Heritage Parkway

  • Project valueTBD
  • Contractor nameTBD
  • Completion DateDecember 13, 2024

Project Update 4/2/2024

  • City of Tea is planning to split this project into two phases one will be constructed in 2024 and another phase will be completed in 2025.
  • Further details on what is getting constructed in 2024 will be updated soon.

Commuter Route Information:

  • 85th Street from Sundowner Avenue to Heritage Parkway will be closed to traffic.
  • Access to local residents only.

Project Milestones

  1. Road Closed
  2. Removals
  3. Watermain
  4. Storm Sewer
  5. Grading
  6. Graveling
  7. Asphalt Surfacing
  8. Restoring
  9. Open to Traffic

Printable Project Overview

Project Overview 85th Street 2024