2024 ADA Accessibility Improvements

  • Project value$1,210,736.55
  • Contractor nameBig Al's Contracting Inc.
  • Completion DateNovember 15, 2024

Project Update 5/2/2024

  • The bid opening for the project occurred on April 11, 2024, and Big Al’s Contracting Inc. was read low at $1,210,736.55.

Commuter Route Information:

There will be intermittent lane closures as part of this project.

Project Milestones

  1. ADA accessibility repairs along the east side of Minnesota Avenue between 33rd Street and 26th Street.
  2. ADA accessibility repairs along the east side of Minnesota Avenue between 26th Street and 18th Street.
  3. ADA accessibility repairs along the west side of Minnesota Avenue between 26th Street and 18th Street.
  4. ADA accessibility repairs along the west side of Minnesota Avenue between 33rd Street and 26th Street.