Pump Station 240 Capacity Improvements Phase 2B - North

  • Project value$19,957,814.34
  • Contractor nameLidel Construction Inc.
  • Completion DateNovember 19, 2025

Project Update 7/1/2024

  • The City of Sioux Falls has awarded the contract for this project to Lidel Construction, Inc. as the general contractor.  Work is scheduled to begin in early August 2024 on the portion of the project located northwest of the intersection of Rice Street and Veterans Parkway.  It is anticipated that the contractor will complete the portion of the sanitary sewer force main between Rice Street and the Water Reclamation Facility by December of 2024 and then work north to south along the east side of Veterans Parkway from Rice Street to 6th Street beginning in the Spring of 2025 until the completion date.

Commuter Route Information

  • Veterans Parkway will be open to traffic throughout the duration of the project. 
  • Closures of the northbound shoulder and northbound right turn lanes on Veterans Parkway will be allowed. 
  • Any closures of through lanes will be minimized to the greatest extent possible and are limited to two weeks and no more than 1000 feet in length. 

  • A full closure of the shared use path / bike trail along the east side of Veterans Parkway will be completed in two segments. 
  • The two segments that will be closed are from the tunnel location north of Madison Street to Maple Street and from Maple Street to Rice Street. 
  • Only one segment will be allowed to be closed at a time.

  • Every effort will be made to minimize travel impacts throughout the duration of the project. 
  • Access to adjacent businesses and residences will be maintained throughout the project.

Project Milestones

Sanitary Sewer Force Main Construction

  1. Install force main from 6th Street to Madison Street
  2. Jack and Bore force main under Madison Street
  3. Removal of shared use path asphalt pavement on east side of Veterans Parkway between Madison Street and Maple Street
  4. Install force main from Madison Street to Maple Street
  5. Grade and gravel shared use path between Madison Street and Maple Street
  6. Asphalt pave shared use path between Madison Street and Maple Street
  7. Site restoration
  8. Removal of shared use path asphalt pavement on east side of Veterans Parkway between Maple Street and Rice Street
  9. Install force main from Maple Street to Rice Street
  10. Jack and Bore force main under Rice Street and Veterans Parkway
  11. Grade and gravel shared use path between Maple Street and Rice Street
  12. Asphalt pave shared use path between Maple Street and Rice Street
  13. Site restoration
  14. Install force main from the intersection of Rice Street and Veterans Parkway to the Sioux Falls Water Reclamation Facility