Pump Station 240 Capacity Improvements Phase 2B - North

  • Project value$19,957,814.34
  • Contractor nameLidel Construction Inc.
  • Completion DateNovember 19, 2025

Project Update: 09/29/2025

  • Lidel Construction has completed jack and bore operations, as well as pipe installation, from the Ellis and Eastern Railroad to the Water Reclamation Facility.
  • The boring operations under Madison Street and Paddington Street are complete. Pipe installation from 6th Street to Maple Street has also been completed. Boring under Maple Street is complete. Pipe installation from Maple Street to Rice Street is currently in progress.
  • Boring under Veterans Parkway, south of Rice Street, is also in progress.

Commuter Route Information

  • Closures along Veterans Parkway for pipe installation.

Project Milestones

Sanitary Sewer Force Main Construction

  1. Install a force main from 6th Street to Madison Street
  2. Jack and Bore force main under Madison Street
  3. Removal of shared-use path asphalt pavement on the east side of Veterans Parkway between Madison Street and Maple Street
  4. Jack and Bore force main under Paddington Street
  5. Install a force main from Madison Street to Maple Street
  6. Jack and Bore force main under Maple Street
  7. Grade and gravel shared-use path between Madison Street and Maple Street
  8. Asphalt-paved shared-use path between Madison Street and Maple Street
  9. Site restoration
  10. Removal of shared-use path asphalt pavement on the east side of Veterans Parkway between Maple Street and Rice Street
  11. Jack and Bore force main under Veterans Parkway
  12. Install a force main from Maple Street to Rice Street
  13. Jack and Bore force main under Rice Street and Veterans Parkway
  14. Grade and gravel shared-use path between Maple Street and Rice Street
  15. Asphalt-paved shared-use path between Maple Street and Rice Street
  16. Site restoration
  17. Jack and Bore force main under Rice Street and Ellis & Eastern Railroad
  18. Jack and Bore force main under the BNSF Railroad
  19. Install a force main under the Big Sioux River
  20. Install a force main from the intersection of Rice Street and Veterans Parkway to the Sioux Falls Water Reclamation Facility