Pump Station 240 Capacity Improvements Phase 2B - North

  • Project value$19,957,814.34
  • Contractor nameLidel Construction Inc.
  • Completion DateNovember 19, 2025

Project Update: 04/29/2025

  • Lidel Construction has completed jack and bore and pipe installation operations from Ellis and Eastern Rail Road to the Water  Recloimation.  Testing and restoration remains. 
  • The contractor has started boring under Veterans Parkway. 

Commuter Route Information

  • Day closures along Veterans Parkway for material delivery.

Project Milestones

Sanitary Sewer Force Main Construction

  1. Install force main from 6th Street to Madison Street
  2. Jack and Bore force main under Madison Street
  3. Removal of shared use path asphalt pavement on east side of Veterans Parkway between Madison Street and Maple Street
  4. Jack and Bore force main under Paddington Street
  5. Install force main from Madison Street to Maple Street
  6. Jack and Bore force main under Maple Street
  7. Grade and gravel shared use path between Madison Street and Maple Street
  8. Asphalt pave shared use path between Madison Street and Maple Street
  9. Site restoration
  10. Removal of shared use path asphalt pavement on east side of Veterans Parkway between Maple Street and Rice Street
  11. Jack and Bore force main under Veterans Parkway
  12. Install force main from Maple Street to Rice Street
  13. Jack and Bore force main under Rice Street and Veterans Parkway
  14. Grade and gravel shared use path between Maple Street and Rice Street
  15. Asphalt pave shared use path between Maple Street and Rice Street
  16. Site restoration
  17. Jack and Bore force main under Rice Street and Ellis & Eastern Railroad
  18. Jack and Bore force main under BNSF Railroad
  19. Install force main under the Big Sioux River
  20. Install force main from the intersection of Rice Street and Veterans Parkway to the Sioux Falls Water Reclamation Facility