Pump Station 240 Capacity Improvements Phase 2B - North

  • Project value$19,957,814.34
  • Contractor nameLidel Construction Inc.
  • Completion DateNovember 19, 2025

Project Update: 08/01/2025

  • Lidel Construction has completed jack and bore operations, as well as pipe installation, from Ellis and Eastern Railroad to the Water Reclamation facility.
  • The boring under Madison Street is complete, and boring under Paddington Street has begun. Pipe installation from 6th Street to Madison Street is also complete.
  • Currently, the contractor is installing pipe from Madison Street to Maple Street. Once they reach Maple Street, they will perform a bore underneath it. 

Commuter Route Information

  • Closures along Veterans Parkway for pipe installation.

Project Milestones

Sanitary Sewer Force Main Construction

  1. Install a force main from 6th Street to Madison Street
  2. Jack and Bore force main under Madison Street
  3. Removal of shared-use path asphalt pavement on the east side of Veterans Parkway between Madison Street and Maple Street
  4. Jack and Bore force main under Paddington Street
  5. Install a force main from Madison Street to Maple Street
  6. Jack and Bore force main under Maple Street
  7. Grade and gravel shared-use path between Madison Street and Maple Street
  8. Asphalt-paved shared-use path between Madison Street and Maple Street
  9. Site restoration
  10. Removal of shared-use path asphalt pavement on the east side of Veterans Parkway between Maple Street and Rice Street
  11. Jack and Bore force main under Veterans Parkway
  12. Install a force main from Maple Street to Rice Street
  13. Jack and Bore force main under Rice Street and Veterans Parkway
  14. Grade and gravel shared-use path between Maple Street and Rice Street
  15. Asphalt-paved shared-use path between Maple Street and Rice Street
  16. Site restoration
  17. Jack and Bore force main under Rice Street and Ellis & Eastern Railroad
  18. Jack and Bore force main under the BNSF Railroad
  19. Install a force main under the Big Sioux River
  20. Install a force main from the intersection of Rice Street and Veterans Parkway to the Sioux Falls Water Reclamation Facility