Pump Station 240 Capacity Improvements Phase 2B - South

  • Project value$14,628,010.78
  • Contractor nameMetro Construction, Inc.
  • Completion DateNovember 19, 2025

Project Complete

Commuter Route Information

Project Milestones

Sanitary Sewer Force Main Construction

  1. Install force main from Pump Station 240 to 900 feet east of Six Mile Road
  2. Connect to existing force main 900 feet east of Six Mile Road
  3. Connect to existing force main 100 feet north of 57th Street
  4. Removal of shared use path asphalt pavement between Harmodon Park tunnel access and 41st Street
  5. Install force main from 57th Street to 41st Street
  6. Jack and Bore force main under 41st Street
  7. Grade and gravel shared use path between tunnel access and 41st Street
  8. Asphalt pave shared use path between tunnel access and 41st Street
  9. Site restoration
  10. Removal of shared use path asphalt pavement between 41st Street and 26th Street
  11. Install force main from 41st Street to 700 feet north of 26th Street
  12. Jack and Bore force main under 26th Street
  13. Grade and gravel shared use path between 41st Street and 26th Street
  14. Asphalt pave shared use path between 41st Street and 26th Street
  15. Site restoration

Grading and Surfacing of 57th Street east of Six Mile Road

  1. Remove existing asphalt and gravel surfacing
  2. Grading
  3. Private Utility Relocation
  4. Storm Sewer installation
  5. Graveling
  6. Asphalt paving
  7. Site restoration