West Mesa Pass Watermain Replacement

  • Project value$1,514355.54
  • Contractor nameBlacktop Paving
  • Completion DateOctober 11, 2024
West Mesa Pass map

Project Update 5/2/2024

  • The Open House hosted April 15, 2024, was attended by a dozen neighborhood residents.
  • Construction on Phase 1 is scheduled to start May 6, 2024 

Commuter Route Information

  • The intersection of West Essex Drive and West Mesa Pass will be closed during Phase 1 construction.
  • Pedestrian access for West Essex Drive will be available along the south side of the intersection.
  • West Mesa Pass’s eastern half will be closed north of the intersection of West Essex Dr and West Mesa Pass during Phase 1 (the pink portion shown on the map).
  • Letters will be mailed to phase 1 property owners informing them of coming construction.

Project Milestones

Phase 1

  1. Traffic Control
  2. Asphalt Removal
  3. Storm Drainage
  4. Sanitary repair
  5. Watermain
  6. Grading/Gravel
  7. Concrete Curb & gutter
  8. Other Concrete work
  9. Milling and Asphalt Pavement
  10. Street Lighting
  11. Seeding/Restoration

Phase 2

  1. Traffic Control
  2. Asphalt Removal
  3. Storm Drainage
  4. Sanitary repair
  5. Watermain
  6. Grading/Gravel
  7. Concrete Curb & gutter
  8. Other Concrete work
  9. Milling and Asphalt Pavement
  10. Street Lighting
  11. Seeding/Restoration

Phase 3

  1. Traffic Control
  2. Asphalt Removal
  3. Storm Drainage
  4. Sanitary repair
  5. Watermain
  6. Grading/Gravel
  7. Concrete Curb & gutter
  8. Other Concrete work
  9. Milling and Asphalt Pavement
  10. Street Lighting
  11. Seeding/Restoration