6th Street, Foss to Veterans

  • Project value$3.3 Million
  • Contractor nameT&R Contracting
  • Completion DateSeptember 19, 2025

Project Update: 04/28/2025

Traffic signal and lighting work has started

Commuter Route Information

  • Open to Traffic. Traffic control in place.

Project Milestones

  1. Traffic Control
  2. Install Erosion Control Measures
  3. Grading
  4. Water Main
  5. Storm Drainage
  6. Concrete Paving
  7. Street Lighting
  8. Sidewalk
  9. Restoration
  10. Traffic Signals