I-29 & 85th Street Interchange

  • Project valueTBD
  • Contractor nameTBD
  • Completion DateDecember 18, 2026

Project Update: 07/01/2025

  • Bid opening for the project is scheduled for September 17, 2025. Right-of-way acquisition along the corridor is currently underway.
  • The project scope includes the construction of the interchange along with underground utility installation, a pedestrian underpass, grading, concrete surfacing, signage, street lighting, and traffic signals.
  • Construction is anticipated to begin later in 2025 and reach completion by early 2027.

Commuter Route Information

  • 85th street from Tallgrass Avenue to Sundowner Avenue will be closed to traffic. Access will be maintained to local residents only.
  • I29 traffic to remain in place during construction. Lane/shoulder closures will be allowed for work adjacent to existing lanes.
  • Partial closures of I29 will be allowed overnight for bridge or MSE wall construction.

Project Milestones

Year 1 - Phase 1A

  1. Traffic Control
  2. Removals
  3. Watermain
  4. Grading
  5. Geofoam Over L&C Watermain
  6. Bridge Abutment
  7. Bridge Pier
  8. Grading Pumps

Year 1 - Phase 1B

  1. Grading Bridge Abutment
  2. Geofoam Over L&C Watermain
  3. MSE Wall
  4. Grading Pumps

Year 1 - Phase 1C

  1. Final Grading
  2. I229 Grade Widening at Ramp 1C
  3. Excavation for Ramp 1C

Year 2 - Phase 2A

  1. Ramp Paving
  2. Bridge Construction
  3. Storm Sewer

Year 2 - Phase 2B

  1. Graveling
  2. Curb and Gutter
  3. Concrete Surfacing

Year 2 - Phase 2C

  1. Lighting
  2. Decorative Landscaping
  3. Pavement Markings
  4. Restoration
  5. Open to Traffic