South Cliff Avenue Concrete Rehab from Big Sioux River Bridge to Tomar

  • Project value$2,060,000
  • Contractor nameBX Civil & Construction
  • Completion DateAugust 15, 2025
Project map image of S Cliff concrete rehab project

Project Update: 06/02/2025

  • In early June, the northbound lanes of Cliff Avenue between the Big Sioux River Bridge and Tomar Road will be closed, with northbound and southbound traffic utilizing the two newly repaired southbound lanes.
  • The contractor will continue working on pavement repair areas, saw cutting, removing, setting forms and placing concrete.

Commuter Route Information

  • Lane closures are in place.  At a minimum, one lane of traffic will remain open in both directions at all times.  Access to businesses, parks and homes will be maintained.  Access to side streets will be maintained if possible.

Project Milestones

  1. Curb & Gutter and Fillet Repairs
  2. Concrete panel and joint repairs
  3. Partial depth pavement repairs
  4. Accessible sidewalk replacement
  5. Seeding & topsoil placement
  6. Diamond grinding of concrete pavement surface
  7. Reseal concrete pavement joints
  8. Pavement markings