Landfill Turn Lane

  • Project value$460,121.71
  • Contractor nameAsphalt Surfacing Co.
  • Completion DateOctober 31, 2025

Project Update: 089/02/2025

Asphalt Surfacing Company has begun construction on Phase 1 along 267th Street (Minnehaha County Hwy 148).

Commuter Route Information

  • 267th Street is currently closed to through traffic for Phase 1 to allow construction crews to work east of the landfill entrance. Access to residents/businesses east of the landfill entrance is via temporary roads.
  • Drivers are urged to use caution, reduce speeds when traveling near the construction area, and follow the signed detour routes for access to the landfill. Construction is expected to continue through October.

Project Milestones

Phase 1:

  1. Removals / Erosion Control
  2. Subgrade/base course
  3. Paving
  4. Top soil/seeding
  5. Striping

Phase 2:

  1. Removals / Erosion Control
  2. Storm Sewer
  3. Subgrade/base course
  4. Paving
  5. Top soil/seeding
  6. Striping