North Drive Bridge Preservation

  • Project valueBridge over BNSF Railway = $444,042.00 | Bridge over Diversion Channel = $1,047,820.00
  • Contractor nameSFC Civil Constructors
  • Completion DateNovember 26, 2025
Project map for the North Bridge Preservation

Project Update: 09/02/2025

Bridge over the diversion channel:

  • The contractor has completed the necessary bridge deck repairs and placed the 2” low-slump concrete overlay on the north half of the bridge.  The process will be repeated for the south half during the first couple of weeks in September.
  • In mid-September, the bridge will be closed to allow for the replacement of the drop inlets, storm sewer pipe, bridge end backfill, and approach slabs.

Bridge over BNSF Railway:

  • Bridge deck repairs have begun. Through the month of September, the bridge deck surface will be ground, deteriorated areas repaired and a polymer chip seal will be placed on the deck surface.

Commuter Route Information

Bridge over the diversion channel:

  • Traffic will be maintained in both directions until mid-September.  The bridge will then be closed to allow for replacement of the drop inlets, storm sewer pipe, bridge end backfill, and approach slabs.
  • The duration of the September closure is estimated to be approximately one month.
  • A detour route utilizing N. 4th Avenue, Benson Road, Minnesota Avenue, and Russell Street will be in place.

Bridge over BNSF Railway:

  • Traffic will be maintained in both directions for the duration of this bridge preservation work.