North Drive Bridge Preservation

  • Project valueBridge over BNSF Railway = $444,042.00 | Bridge over Diversion Channel = $1,047,820.00
  • Contractor nameSFC Civil Constructors
  • Completion DateNovember 26, 2025
Project map for the North Bridge Preservation

Project Update: 08/01/2025

  • This project is scheduled to begin on August 11.
  • Work will begin on the bridge over the diversion channel.  This bridge is to receive a low-slump dense concrete overlay, new approach slabs, new drop inlets with new concrete pipe, and corrugated metal pipe installed from the street to the diversion channel.

Commuter Route Information

  • Traffic will be maintained in both directions until mid-September.  The bridge over the diversion channel will then be closed to allow for replacement of the approach slabs, drop inlets, and pipe.
  • The duration of the September closure is estimated to be approximately one month.
  • A detour route utilizing N. 4th Avenue, Benson Road, Minnesota Avenue, and Russell Street will be in place.