Veterans Concrete Restoration & Joint Reseal from Arrowhead to 26th

  • Project value$528,447.45
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 14, 2025
Veteran's Arrowhead to 26th St. Project Map

Project Update: 04/28/2025

  • Project has been bid and awarded.  A preconstruction meeting is being scheduled.
  • Construction will start mid to late May.
  • Work will include full depth concrete patching, curb and gutter repair and joint re-sealing.

Commuter Route Information

  • Lane closures will be in place. 
  • At a minimum, one lane of traffic will remain open in both directions at all times.

Project Milestones

  1. Curb & gutter and fillet repairs
  2. Concrete panel and joint repairs
  3. Seeding & topsoil placement
  4. Application of soy based penetrating sealer
  5. Reseal concrete pavement joints