Veterans Concrete Restoration & Joint Reseal from Arrowhead to 26th

  • Project value$528,447.45
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 14, 2025
Veteran's Arrowhead to 26th St. Project Map

Project Update: 08/01/2025

  • Concrete repairs and joint resealing are complete in the northbound and southbound outside lanes and shoulders.
  • Currently, the northbound and southbound inside lanes are closed, and the contractor is working on full-depth concrete repairs.  Traffic is being maintained in the outside lanes in both directions.
  • After the concrete repairs in the inside lanes are complete, the process of resealing the pavement joints will begin.  First, the old sealant is cleaned out of the joint. Next, a soy-based concrete sealer is applied, and finally, the joints are resealed with hot-pour joint sealer.
  • The project is anticipated to be completed by late August.

Commuter Route Information

  • Lane closures are in place.
  • At a minimum, one lane of traffic will remain open in both directions at all times.  Access to businesses, homes and side streets will be maintained.

Project Milestones

  1. Curb & gutter and fillet repairs
  2. Concrete panel and joint repairs
  3. Seeding & topsoil placement
  4. Application of soy based penetrating sealer
  5. Reseal concrete pavement joints