This project is anticipated to begin on Monday, April 6. Crews will be performing curb and gutter repairs and repairs on the concrete pavement at both the 26th Street and 41st Street intersections with Veterans Parkway.
Lane closures will be in place. At a minimum, one lane of traffic will remain open in both directions at all times.
PHASE 1A: 41st Street outside lane(s) and Veterans Parkway & 41st Street intersection
PHASE 1B: 41st Street inside lane(s) and Veterans Parkway & 41st Street intersection
PHASE 1C: Veterans Parkway & 41st Street - middle of the intersection
PHASE 2A: Veterans Parkway outside lanes & 33rd Street intersection
PHASE 2B: Veterans Parkway - inside lanes
PHASE 3A: Veterans Parkway & 26th Street intersection outside lane(s)
PHASE 3B: Veterans Parkway & 26th Street intersection - inside lane(s)
PHASE 3C: Veterans Parkway & 26th Street middle of the intersection
DGR Engineering
Aaron Miller Email: aaron.miller@dgr.com Phone: 605-214-0146
Sign up to receive Monthly Street Construction News
This project will consist of concrete joint and panel repairs, curb and gutter repairs, joint re-sealing, and application of soy-based penetrating sealer on Veterans Parkway from E. 26th Street to E. 41st Street.