NOTICE: To accommodate attendees of the Sioux Falls Airshow on July 18th and 19th, beginning on Thursday, July 16 at 8:00 pm all traffic control will be removed from the lanes of travel on Russell Street from Minnesota Avenue to I-29 northbound on ramp. All lanes will be open to traffic until 6:00 am on Monday, July 20.
Phase 1: Asphalt overlay at the intersection of Russell Street and Westport/Louise Avenue
Phase 2: Eastbound Russell Street from approximately Howard Wood Field to Minnesota Avenue
Phase 3: Westbound Russell Street from Minnesota Avenue to approximately Howard Wood Field
Phase 4: Westbound Russell Street from approximately Howard Wood Field to I29 northbound on-ramp
Phase 5: Eastbound Russell Street from N. Louise Drive to approximately Howard Wood Field
Crews repairing curb an gutter
Crews resealing concrete joints
Crews performing partial-dpeth concrete repairs
Crews applying a soy based sealant to the new concrete
Marshall Engineering Inc.
Marshall Runge Phone: 605-338-5736 Email: Marshall.MarshallEng@midconetwork.com
Sign up to receive Monthly Street Construction News
This project will rehabilitate W. Russell Street from N. Louise Drive to N. Minnesota Avenue. Work will include full-depth concrete patching, partial-depth concrete patching, curb and gutter repair, and joint re-sealing. The intersection of W. Russell Street and Westport/Louise Drive will receive an asphalt overlay.