Russell Street Pavement Restoration - N. Louise Dr. to Minnesota Ave

  • Project value$2,398,831.87
  • Contractor nameReede Construction, Inc.
  • Completion DateOctober 09, 2026

Project Update: 11/02/2026

  • This concrete repair project is complete.  The contractor completed approximately 2,700 square yards of concrete pavement repairs, 5,200 linear feet of curb and gutter repairs, and re-sealed 114,000 linear feet of concrete pavement joints.

    This will be the final upate for this project

Commuter Route Information

  • In the upcoming weeks, the location of the lane closures on Russell Street will vary between Louise Drive and Western Avenue.  At a minimum, one lane of traffic will remain open at all times through the work zone.  Access to businesses, homes and side streets will be maintained.

Project Location Map

Russell Street concrete map

Project Phasing Diagram

Russell Street concrete phasing diagram

 

Project Milestones

Phase 1: Asphalt overlay at the intersection of Russell Street and Westport/Louise Avenue

  1. Curb & gutter repairs
  2. Cold milling concrete pavement
  3. 3/4" Asphalt scratch course
  4. 1 1/2" Asphalt overlay
  5. Pavement markings

Phase 2: Eastbound Russell Street from approximately Howard Wood Field to Minnesota Avenue

  1. Curb & gutter and fillet repairs
  2. Full-depth concrete panel and joint repairs
  3. Partial depth pavement repairs
  4. Accessible sidewalk replacement
  5. Seeding & topsoil placement
  6. Application of soy-based penetrating sealer
  7. Reseal concrete pavement joints

Phase 3: Westbound Russell Street from Minnesota Avenue to approximately Howard Wood Field

  1. Curb & gutter and fillet repairs
  2. Full-depth concrete panel and joint repairs
  3. Partial depth pavement repairs
  4. Accessible sidewalk replacement
  5. Seeding & topsoil placement
  6. Application of soy-based penetrating sealer
  7. Reseal concrete pavement joints

Phase 4: Westbound Russell Street from approximately Howard Wood Field to I29 northbound on-ramp

  1. Curb & gutter and fillet repairs
  2. Full-depth concrete panel and joint repairs
  3. Partial depth pavement repairs
  4. Accessible sidewalk replacement
  5. Seeding & topsoil placement
  6. Application of soy-based penetrating sealer
  7. Reseal concrete pavement joints

Phase 5: Eastbound Russell Street from N. Louise Drive to approximately Howard Wood Field

  1. Curb & gutter and fillet repairs
  2. Full-depth concrete panel and joint repairs
  3. Partial depth pavement repairs
  4. Accessible sidewalk replacement
  5. Seeding & topsoil placement
  6. Application of soy-based penetrating sealer
  7. Reseal concrete pavement joints