I-29 & 85th Street Interchange

  • Project value$54,443,975
  • Contractor nameT&R Contracting
  • Completion DateDecember 31, 2027
Concept image of the 85th I29 Intechange

The City of Sioux Falls, in conjunction with the City of Tea, Lincoln County, and the SDDOT, has started constructing the new diverging diamond interchange at 85th Street and I-29.

The project includes building the interchange and installing underground utilities, a pedestrian underpass, grading, concrete surfacing, signage, street lighting and traffic signals.

Project Update: 05/5/2026

  • The contractor will continue grading 85th Street east and west of I-29.
  • The contractor is continuing to install bridge pilings for the 85th Street bridge.
  • The contractor plans to install the water main on the west side of the interstate in June.

Commuter Route Information

  • 85th Street from Tallgrass Avenue to Sundowner Avenue will be closed to traffic. Access will be maintained for local residents only.

  • I29 traffic to remain in place during construction. Lane/shoulder closures will be allowed for work adjacent to existing lanes.

  • Partial closures of I29 will be allowed overnight for bridge or MSE wall construction.

Additional Information

Project Milestones

Year 1 - Phase 1A

  1. Traffic Control
  2. Removals
  3. Watermain
  4. Grading
  5. Geofoam Over L&C Watermain
  6. Bridge Abutment
  7. Bridge Pier
  8. Grading Pumps

Year 1 - Phase 1B

  1. Grading Bridge Abutment
  2. Geofoam Over L&C Watermain
  3. MSE Wall
  4. Grading Pumps

Year 1 - Phase 1C

  1. Final Grading
  2. I229 Grade Widening at Ramp 1C
  3. Excavation for Ramp 1C

Year 2 - Phase 2A

  1. Ramp Paving
  2. Bridge Construction
  3. Storm Sewer

Year 2 - Phase 2B

  1. Graveling
  2. Curb and Gutter
  3. Concrete Surfacing

Year 2 - Phase 2C

  1. Lighting
  2. Decorative Landscaping
  3. Pavement Markings
  4. Restoration
  5. Open to Traffic