The grading contractor will continue work on the northbound Interstate 229.
The retaining wall contractor in constructing a 650-foot-long mechanically stabilized earth (MSE) retaining wall along the south side of the northbound on-ramp, followed by a 180-foot-long MSE wall between the northbound on-ramp and the interstate.
Sanitary sewer installation is complete.
Bridge crews are currently constructing bridge bents for the northbound bridge.
Girders are currently planned to be installed in early July.
Paving of the northbound lanes on the west side of I-229 and the southbound lanes of Cliff Avenue is planned for July.