Southeast Basins Sanitary Sewer Installation along Co Highway 106

  • Project value$10,299,263.38
  • Project schedule2027
  • Contractor nameLidel Construction

Project Update: 06/30/2026

Construction is expected to begin in late July along Lincoln County Highway 106 between Cliff Avenue and Southeastern Avenue.  A public open house will be held prior to construction.

Commuter Route Information

  • Lincoln County Highway 106 will be closed between Cliff Avenue and Southeastern Avenue once construction begins in July and will remain closed until November. Traffic will be detoured to 57th Street.

  • Additional closures will be in place in 2027 between Cliff Avenue and Minnesota Avenue, and between Minnesota Avenue and Western Avenue.

Project Milestones

Phase 1A - Cliff Avenue to Southeastern Avenue

  1. BNSF boring
  2. Cliff Ave boring
  3. Sanitary Sewer west of Cliff Ave
  4. Sanitary Sewer between Cliff Ave and BNSF Railroad
  5. Sanitary Sewer between BNSF Railroad and Southeastern Ave
  6. Cement-treated base
  7. Asphalt paving
  8. Restoration

Phase 1B - Minnesota Avenue to Cliff Avenue

  • 2027 Construction 

Phase 1C Western Avenue to Minnesota Avenue

  • 2027 Construction