Southeast Basins Sanitary Sewer Installation along Co Highway 106

  • Project value$10,299,263.38
  • Project schedule2027
  • Contractor nameLidel Construction
  • Completion DateOctober 29, 2027

Project Update: 11/02/2026

The casing pipe underneath the BNSF Railroad has been completed. The Cliff Avenue crossing is complete. Lincoln County Highway 106 should reopen by the end of November.

Commuter Route Information

  • Lincoln County Highway 106 is closed between Cliff Avenue and Southeastern Avenue and will remain closed until November. Traffic is being detoured to 57th Street.
  • Additional closures will be in place in 2027 between Southeastern Avenue and Minnesota Avenue, and between Minnesota Avenue and Western Avenue.
Southeast Basins Detour Route 2026

Project Milestones

Phase 1A - Cliff Avenue to Southeastern Avenue

  1. BNSF boring
  2. Cliff Ave boring
  3. Sanitary Sewer west of Cliff Ave
  4. Sanitary Sewer between Cliff Ave and BNSF Railroad
  5. Sanitary Sewer between BNSF Railroad and Southeastern Ave
  6. Temporary Asphalt Patching
  7. Cement-treated base
  8. Asphalt paving
  9. Restoration

Phase 1B - Minnesota Avenue to Cliff Avenue

  • 2027 Construction

Phase 1C Western Avenue to Minnesota Avenue

  • 2027 Construction