Southeast Basins Sanitary Sewer Installation along Co Highway 106

  • Project value$10,299,263.38
  • Project schedule2027
  • Contractor nameLidel Construction
  • Completion DateOctober 29, 2027

Project Update: 08/31/2026

Construction will begin on August 31, 2026 along Lincoln County Highway 106 between Cliff Avenue and Southeastern Avenue.  Construction will involve installing casing pipes under Cliff Ave and the BNSF railroad, and a gravity sewer from the railroad to Southeastern Ave

Commuter Route Information

  • Lincoln County Highway 106 will be closed between Cliff Avenue and Southeastern Avenue once construction begins in August/September and will remain closed until November. Traffic will be detoured to 57th Street.

  • Additional closures will be in place in 2027 between Southeastern Avenue and Minnesota Avenue, and between Minnesota Avenue and Western Avenue.

Southeast Basins Detour Route 2026

Project Milestones

Phase 1A - Cliff Avenue to Southeastern Avenue

  1. BNSF boring
  2. Cliff Ave boring
  3. Sanitary Sewer west of Cliff Ave
  4. Sanitary Sewer between Cliff Ave and BNSF Railroad
  5. Sanitary Sewer between BNSF Railroad and Southeastern Ave
  6. Temporary Asphalt Patching
  7. Cement-treated base
  8. Asphalt paving
  9. Restoration

Phase 1B - Minnesota Avenue to Cliff Avenue

  • 2027 Construction

Phase 1C Western Avenue to Minnesota Avenue

  • 2027 Construction