Underground work is complete at the far east end of 42nd Street. Underground work starting at the far west of 42nd Street and moving east. Grading will follow the underground work.
42nd Street will be closed to traffic within the work area.
Walkway paths and parking areas are complete for both 42nd Street and 46th Street.
42nd Street from Klein Avenue to 1500 feet east
46th Street, Ellis Road to Klein Avenue
City of Sioux Falls Public Works - Engineering
John Osman Email: John.Osman@SiouxFalls.gov Phone: 605-367-8640
Sign up to receive Monthly Street Construction News
Installation of new sanitary sewer and watermain. Restablish ditch drainage grading and installation of new storm drainage culverts. Construction of a rural roadway with asphalt paving and restoration.