Benson Road / I-229 Interchange Reconstruction

  • Project value$36,360,596.00
  • Contractor nameT&R Contracting, Inc.
  • Completion DateJune 27, 2025
benson-webpage-banner

Project Update 4/2/2024  

  • Construction has begun on Benson Road.
  • Pavement removals have been completed and underground utility work is underway. 

Commuter Route Information: 

  • Traffic is reduced to one lane in each direction. 

Project Milestones

Year 2023

  1. Bridge work
  2. Pavement removals
  3. Watermain installation
  4. Sanitary sewer repairs & installation
  5. Storm drainage improvements
  6. Grading
  7. Gravelling
  8. Concrete Paving
  9. Driveways, approaches, curb ramp, and sidewalk construction
  10. End bridge work
  11. Restoration

Year 2024  Phase 1

  1. Bridge deck work
  2. Pavement removals
  3. Watermain installation
  4. Sanitary sewer repairs & installation
  5. Storm drainage improvements
  6. Grading
  7. Gravelling
  8. End bridge deck work
  9. Concrete Paving
  10. Driveways, approaches, curb ramp, and sidewalk construction
  11. Restoration

Year 2024 – Phase 2 (median)

  1. Grading
  2. Graveling
  3. Concrete Paving

Year 2024 – Phase 3 (interchange islands)

  1. Grading
  2. Gravelling
  3. Concrete Paving