72nd Street North- North Seubert Avenue to 476th Avenue

  • Project value$1,180,109.81
  • Contractor nameSiteworks, Inc.
  • Completion DateNovember 14, 2025

72nd Street Project Map Image

Project Update: 09/29/2025

Construction started end of September at the west end of 72nd Street near Seubert Avenue, with the contractor removing pavement and clearing trees along 72nd Street.

Boring crews plan to start working to install the casing pipe for the watermain to install under 476th early October. Construction is expected to be completed in late November, with some final seeding done in the spring of 2026.

Commuter Route Information

72nd Street North is closed to through traffic, but local access for residents and property owners along 72nd Street North will be maintained during construction. The detour route is to 258th Street and I-90 via 476th Avenue and SD Highway 115 (Cliff Avenue).

Project Milestones 

  1. Traffic Control
  2. Clearing & Grubbing
  3. Removals
  4. Watermain Installation
  5. Sanitary Sewer Installation
  6. Storm Drainage Installation
  7. Grading
  8. Surfacing
  9. Seeding / Restoration