Minnesota Avenue from 2nd Street to 8th Street Reconstruction

  • Project value$12,241,812.80
  • Contractor nameD&G Concrete Construction, Inc.
  • Completion DateJune 25, 2027
Rendering of Minnesota Avenue Phase 2 improvements

Project Update: 02/18/2026

A construction open house will be held on Thursday, February 26, 2026, from 5:30 pm to 7:00 pm at City Center, 231 N. Dakota Avenue, in the Cooper Room on the first floor.

The public is welcome to attend at any time during the open house; this is an informal event with no presentation. Representatives from HDR and the City will be available to answer questions from the public about the project. If an ADA accommodation is needed, please contact the City of Sioux Falls Human Relations Office at 605-367-8745 or human.relations@siouxfalls.gov at least 72 hours before the event.

Commuter Route Information

  • Phase 1A – the east side of Minnesota Avenue from 2nd Street to 4th Street will be closed
    • The west side of Minnesota Avenue will be open for head-to-head traffic
    • No eastbound turns will be allowed; follow marked detours for business access
  • Phase 2A – the west side of Minnesota Avenue from 2nd Street to 4th Street will be closed
    • The east side of Minnesota Avenue will be open for head-to-head traffic
    • No westbound turns will be allowed; follow marked detours for business access
  • Phase 1B – east side of Minnesota Avenue from 4th Street to 8th Street will be closed
    • The west side of Minnesota Avenue will be open for head-to-head traffic
    • No eastbound turns will be allowed; follow marked detours for business access
  • Phase 2B – the west side of Minnesota Avenue from 4th Street to 8th Street will be closed
    • The east side of Minnesota Avenue will be open for head-to-head traffic
    • No westbound turns will be allowed; follow marked detours for business access
  • Phase 3A – the inside lanes of Minnesota Avenue from Bennett Street to 2nd Street will be closed
  • Phase 3 – the inside lanes of Minnesota Avenue from 2nd Street to 8th Street will be closed
Minnesota Avenue phase 2

Project Milestones

Phase 1A – 2nd Street to 4th Street (center utilities and east side of Minnesota Ave)

  1. Temporary Traffic Signals at the intersections of 2nd Street and 6th Street.
  2. Install traffic control
  3. Install erosion control
  4. 12" Water main
  5. Sanitary sewer
  6. Storm drainage
  7. Traffic conduit
  8. Grading & gravel
  9. Concrete pavement
  10. Sidewalk
  11. Restoration

Phase 2A – 2nd Street to 4th Street (west side of Minnesota Ave)

  1. Install traffic control
  2. Install erosion control
  3. 42" Water main
  4. 8" Water main
  5. Storm drainage
  6. Traffic conduit
  7. Grading & gravel
  8. Concrete pavement
  9. Sidewalk
  10. Restoration

Phase 1B – 4th Street to 8th Street (center utilities and west side of Minnesota Ave)

  1. Temporary Traffic Signals at the intersections of 2nd Street and 6th Street.
  2. Install traffic control
  3. Install erosion control
  4. 12" Water main
  5. Sanitary sewer
  6. Storm drainage
  7. traffic conduit
  8. Grading & gravel
  9. Concrete pavement
  10. Sidewalk
  11. Restoration

Phase 2B – 4th Street to 8th Street (west side of Minnesota Ave)

  1. Install traffic control
  2. Install erosion control
  3. 42" Water main
  4. 8" Water main
  5. Storm drainage
  6. Traffic conduit
  7. Grading & gravel
  8. Concrete pavement
  9. Sidewalk
  10. Restoration

Phase 3A – (Remove, salvage, replace median from 2nd St to Bennett St)

  1. Install traffic control
  2. Remove and salvage the existing low-profile median
  3. Install proposed median pavement within the phase limits

Phase 3 – (median of Minnesota Ave)

  1. Install traffic control
  2. Concrete pavement