8th Street & 3rd Street and Weber Avenue Railroad Crossing Improvement

  • Project value$1,551,407.13
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 27, 2026

Project Update: 06/30/2026

  • The utility work has been completed on the east side of the railroad and paving is underway.

  • Utility work is now underway on the west side of the railroad.

  • Work on 8th Street is underway and is anticipated to be completed by mid-August.

Commuter Route Information

  • 8th Street is now closed to traffic and will remain closed through mid- August while construction is completed.

Project Milestones

  1. 8th Street concrete work near Weber Avenue
  2. 8th Street railroad crossing improvements near Weber Avenue
  3. Weber Avenue concrete work near 3rd Street
  4. Weber Avenue railroad crossing improvements near 3rd Street