Arrowhead Parkway and Veterans Parkway Improvements

  • Project value$39,231,240.02
  • Contractor nameT&R Contracting, inc.
  • Completion DateMay 14, 2027

Project Update: 04/10/2026

The contractor is currently working on grading the two eastbound lanes of Arrowhead Parkway from Veterans Parkway to Hein Avenue. The concrete paving of this section is scheduled to be completed in the next few weeks.

Beginning Monday, April 20, Arrowhead Parkway from Veterans Parkway to Hein Avenue will be closed.  The contractor will remove the temporary asphalt transition that was put in place last fall, and then grade and pave the two northbound lanes of Veterans Parkway and make the connection to Arrowhead Parkway going east. This closure will be in place for approximately 6 weeks.

When all the concrete paving is completed, the east side of the intersection will reopen to traffic, and the west side of the intersection will be closed (between Highline Avenue and Veterans Parkway).  This will allow the contractor to finish the work on the west side of the intersection. All lanes are expected to reopen to traffic in late 2026.

Commuter Route Information

2026

  • Arrowhead Parkway will close east of Veterans Parkway for about 6 weeks beginning April 20. Arrowhead Parkway west of Veterans Parkway will remain open. Veterans Parkway will also remain open.

Current Detour Map

April 2026 Detour Map

(View PDF of the Detour Map)

2027

  • Periodic lane closures may occur in the spring of 2027 as work is finalized and general site cleanup occurs.

Project Milestones

2025

  1. Temporary traffic signals/traffic control
  2. Removals
  3. Rough Grading
  4. Resurface existing Highway 42 for frontage road
  5. Water main - 6th Street to Staudenmier Place
  6. Sanitary Sewer
  7. Casing pipe for the force main through the intersection
  8. Force main - Arrowhead Parkway to 6th Street
  9. Force main - Arrowhead Parkway to 26th Street
  10. Water main
  11. Pedestrian underpasses
  12. Storm drainage piping and structures
  13. Retaining walls
  14. Finish grading
  15. Gravel base preparation/installation
  16. Concrete paving - westbound lanes, 10th to Hein Avenue
  17. Concrete paving - westbound lanes, Hein Avenue to Veterans Parkway
  18. Temporary Transition - Arrowhead Parkway

2026

  1. Traffic control
  2. Removals
  3. Casing pipe for the force main through the intersection
  4. Water main - Arrowhead Parkway to Staudenmeier Place
  5. Water main - Arrowhead Parkway to 26th Street
  6. Storm drainage piping and structures
  7. Retaining walls
  8. Pedestrian underpasses
  9. Finish gradng
  10. Gravel base preparation/installation
  11. Concrete paving - eastbound lanes, Veterans Parkway to 10th Street
  12. Concrete paving - eastbound lanes, Veterans Parkway to Highline Avenue
  13. Concrete paving - westbound lanes, Veterans Parkway to Highline Avenue
  14. Concrete paving - southbound lane, Veterans Parkway
  15. Concrete paving - northbound lanes, Veterans Parkway
  16. Sidewalks
  17. Medians
  18. Street Lighting
  19. Traffic Signals
  20. Signage
  21. Pavement Markings
  22. Site Restoration