This project will include the milling of the existing asphalt street surfacing and the placement of new asphalt street surfacing.
The project is set to begin with asphalt milling on July 7th. The contractor will then proceed to work on any areas that need to be patched before placing an asphalt overlay. All work should be completed by the end of July.
Project Milestones
Marshall Engineering
Marshall Runge – Project Manager Phone: 605-940-0343 Email: marshall.marshalleng@midconetwork.com
Sign up to receive Monthly Street Construction News
This project consists of the milling and asphalt overlay along East 60th Street North from Cliff Avenue to Interstate 229 due to the current pavement condition. Included with this work will be the adjustment of existing water valves and sanitary sewer manholes, along with pavement markings.