72nd Street North- North Seubert Avenue to 476th Avenue Phase 2

  • Project value$1,734,331.01
  • Project scheduleNovember 30, 2026
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 30, 2026

Project Update: 08/31/2026

The intersection of 476th Avenue and 72nd Street North (Phase A) will be open in early September. It’s currently closed from I-90 Frontage Road to Slip Up Creek Road while the contractor finishes grading and paving. After the intersection is completed, the contractor will finish sanitary sewer and storm drainage installation along 72nd Street North and plans to finish paving by the end of September.

Commuter Route Information

  • 72nd Street North is currently closed to through traffic. The detour route is to 258th Street and I-90 via 476th Avenue and SD Highway 115 (475th Avenue).
  • Northbound 476th Avenue is closed from I-90 Frontage Road to Slip Up Creek Road. The detour route is to use 258th Street to/from SD Highway 115 (475th Avenue). Signage for the SD Veterans Cemetery, Laurel Ridge Barn Event Center, and Mapleton Golf Club is noted on the detour route, including northbound I-229. See the detour sketch
72nd Street Detour Map

Project Milestones

Phase A - 72nd Street North & 476th Avenue Intersection

  1. Traffic Control
  2. Removals
  3. Water main installation
  4. Sanitary Sewer Installation
  5. Storm Drainage Installation
  6. Grading
  7. Paving 

Phase B - 72nd Street North

  1. Traffic Control
  2. Clearing & grubbing
  3. Removals
  4. Water main installation
  5. Sanitary Sewer Installation
  6. Storm Drainage Installation
  7. Grading
  8. Paving 
  9. Restoration