72nd Street North- North Seubert Avenue to 476th Avenue Phase 2

  • Project value$1,734,331.01
  • Project scheduleNovember 30, 2026
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 30, 2026

Project Update: 11/02/2026

Paving is complete, but the gravel shoulder still needs to be installed, along with some permanent erosion control in the ditches. The road should be open to traffic the second or third week in November, weather dependent.

Commuter Route Information

  • 72nd Street North is currently closed to through traffic. The detour route is to 258th Street and I-90 via 476th Avenue and SD Highway 115 (475th Avenue). 

Project Milestones

Phase A - 72nd Street North & 476th Avenue Intersection

  1. Traffic Control
  2. Removals
  3. Water main installation
  4. Sanitary Sewer Installation
  5. Storm Drainage Installation
  6. Grading
  7. Paving

Phase B - 72nd Street North

  1. Traffic Control
  2. Clearing & grubbing
  3. Removals
  4. Water main installation
  5. Sanitary Sewer Installation
  6. Storm Drainage Installation
  7. Grading
  8. Paving 
  9. Restoration