72nd Street North- North Seubert Avenue to 476th Avenue Phase 2

  • Project value$1,734,331.01
  • Project scheduleNovember 30, 2026
  • Contractor nameBlack-Top Paving Company
  • Completion DateNovember 30, 2026

Project Update: 06/30/2026

Construction started on June 29th on 72nd Street North (Phase B). 72nd Street North is closed to through traffic throughout construction; however, local access for residents and property owners along 72nd Street North will be maintained during construction.

The intersection of 476th Avenue and 72nd Street North (Phase A) will be closed for about a month starting in mid-to-late July from 72nd Street North to Slip Up Creek Road – the exact start date will be communicated on message boards a week prior to the closure, as well as updated on this webpage.

Commuter Route Information

  • 72nd Street North is currently closed to through traffic. The detour route is to 258th Street and I-90 via 476th Avenue and SD Highway 115 (475th Avenue).
  • In mid-to-late July, 476th Avenue will be closed for about a month from 72nd Street North to Slip Up Creek Road. The detour route is to use 258th Street to/from SD Highway 115 (475th Avenue). Signage for the SD Veterans Cemetery, Laurel Ridge Barn Event Center, and Mapleton Golf Club will be along the detour route, including northbound I-229.

Project Milestones

Phase A - 72nd Street North & 476th Avenue Intersection

  1. Traffic Control
  2. Removals
  3. Water main installation
  4. Sanitary Sewer Installation
  5. Storm Drainage Installation
  6. Grading
  7. Paving 

Phase B - 72nd Street North

  1. Traffic Control
  2. Clearing & grubbing
  3. Removals
  4. Water main installation
  5. Sanitary Sewer Installation
  6. Storm Drainage Installation
  7. Grading
  8. Paving 
  9. Restoration