69th Street from Louise Avenue to Landau Circle

  • Project valueEngineer’s Estimate = $550,000
  • Project scheduleTBD
  • Contractor nameTBD

Project Update: 04/01/2026

Bids for this project are due early April.

Commuter Route Information

  • One lane of traffic will be maintained in each direction.
  • Short-term closures are expected when completing the intersection overlay.

Project Milestones

  1. Traffic Control
  2. Outside Lanes Miling
  3. Outside Lanes Overlay
  4. Inside Lanes Milling
  5. Inside Lanes Overlay