Bridge Preservation Projects - 12th Street

  • Project value$431,369.61
  • Project scheduleWithin 40 working days and by October 30, 2026
  • Contractor nameSFC Civil Constructors
  • Completion DateOctober 30, 2026
12th Street Bridge Project Map

Project Update: 04/01/2026

This project is anticipated to start in mid-May.

Commuter Route Information

  • Lane closures will be in place.  At a minimum, one lane of traffic will remain open in both directions at all times.  At most times throughout the project, two lanes of traffic will be open in both directions.

Project Milestones

12th Street Bridge Project phase 1

Phase 1 – eastbound and westbound outside single lanes closed

  1. Concrete bridge deck repair
  2. Polymer chip seal
  3. Replace the strip seal joint at the ends of the bridge
  4. Special surface finish
  5. Repair the retaining wall coping section
  6. Trim trees
  7. Replace the chain link fence
12th Street Bridge Project phase 2

Phase 2 – eastbound and westbound inside lanes closed

  1. Concrete bridge deck repair
  2. Polymer chip seal
  3. Replace the strip seal joint at the ends of the bridge
  4. Install permanent pavement markings