Water Transmission Main Installation - Phase 2

  • Project valuePhase 2A = $3,201,598.50 Phase 2B & 2C = $3,309,160.20
  • Contractor namePhase 2A = Siteworks, Inc.; Phases 2B & 2C = Alliance Construction
  • Completion DateJune 18, 2027

Project Update: 10/02/2026

  • Phase 2A
    • Water pipe installation is planned to be completed early to mid October. Topsoil will be installed and seeded.
  • Phase 2B & 2C
    • Alliance Construction has started grading at the water meter building site (Phase 2B) and plans to work on the building foundation.

Commuter Route Information

  • 467th Avenue is closed for about two weeks to allow the contractor to install water pipes across 467th Avenue. Traffic is detoured to 266th Street / 22nd Street

Project Milestones

Phase 2A - Pipeline

  1. Traffic Control
  2. Bore under Highway 42
  3. Bore underneath wetlands
  4. Install water main
  5. Grading
  6. Seeding / Restoration
Phase 2A Location Map

12th Street Watermain Installation – Phase 2

Phase 2B - Water Meter Building

    • Grading
    • Install sanitary sewer
    • Install water main
    • Construct building
    • Install mechanical, electrical, and plumbing systems in the building
    • Parking lot and road grading
    • Connect to Lewis and Clark mainline
    • Seeding and restoration
a diagram pf the project map 2B and 2C steps

Phase 2C - West Reservoir Connection

  1. Demolition
  2. Install water pipes
  3. Install electrical controls