Water Transmission Main Installation - Phase 2

  • Project valuePhase 2A = $3,201,598.50 Phase 2B & 2C = $3,309,160.20
  • Contractor namePhase 2A = Siteworks, Inc.; Phases 2B & 2C = Alliance Construction
  • Completion DateJune 18, 2027

Project Update: 11/02/2026

  • Phase 2A
    • Construction is complete.
  • Phase 2B & 2C
    • Alliance Construction has started grading at the water meter building site (Phase 2B) and plans to continue working on the building foundation.

Commuter Route Information

  • No disruption to commuter traffic at this time. 467th Avenue will be closed for about two weeks in early December to allow the contractor to connect to the Lewis and Clark transmission water main.

Project Milestones

Phase 2A - Pipeline

  1. Traffic Control
  2. Bore under Highway 42
  3. Bore underneath wetlands
  4. Install water main
  5. Grading
  6. Seeding / Restoration
Phase 2A Location Map

12th Street Watermain Installation – Phase 2

Phase 2B - Water Meter Building

    • Grading
    • Install sanitary sewer
    • Install water main
    • Construct building
    • Install mechanical, electrical, and plumbing systems in the building
    • Parking lot and road grading
    • Connect to Lewis and Clark mainline
    • Seeding and restoration
a diagram pf the project map 2B and 2C steps

Phase 2C - West Reservoir Connection

  1. Demolition
  2. Install water pipes
  3. Install electrical controls

Project Photos