Louise Avenue from 49th Street to 53rd Street ADA Improvements

  • Project value$382,085.55
  • Contractor nameQ and E Handyman Services
  • Completion DateNovember 30, 2026

Project Update: 06/01/2026

  • Work is completed on the east side of Louise Avenue.
  • Work on the west side of Louise Avenue is planned to be completed in early June.
  • This will be the last project update for this project.

Commuter Route Information

  • Northbound traffic on Louise Avenue will be reduced to one lane. Southbound traffic will not be impacted at this time.

Project Milestones

  1. ADA accessibility repairs along the West side of Louise Avenue between 49th Street and 53rd Street.
  2. ADA accessibility repairs along the East side of Louise Avenue from 53rd Street to 49th Street.

Construction Images

Louise Avenue ADA sidewalk improvements

Lousie Avenue sidewalk improvements.

Louise Avenue ADA sidewalk improvements

Louis Avenue sidewalk and ADA improvements.